IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

In the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the scope baseline and project document update. Which of the following truly represents the scope baseline?
  1. Scope statement, scope management plan, schedule baseline
  2. Scope statement, WBS, WBS dictionary
  3. WBS, WBS dictionary
  4. Scope statement, WBS, schedule baseline






Q2. A project manager prepared a presentation that included data on the project’s use of resources, improvements in staff efficiency, and the cost savings. These activities are part of what process?

  1. Manage Stakeholder Engagement
  2. Monitor and Control Project Work
  3. Control Schedule
  4. Control Quality
Correct Answer

Q3. Project A has had ineffective project meetings since its inception. There have been complaints that information does not get to the right people, some people are talking too much during meetings, and the right people are not there to resolve the issues. What is MOST likely missing from this project?

  1. A scope management plan
  2. A staffing management plan
  3. A communications management plan
  4. A process improvement plan
Correct Answer

Q4. Your project is ahead of schedule but over budget. Therefore, you ask your team member to collect data and compare it with the cost baseline. Which of the following is not included in the cost baseline?

  1. Contingency reserve
  2. Activity cost estimation
  3. Management reserve
  4. Activity contingency reserve
Correct Answer

Q5. A project manager overhears a conversation between two stakeholders who are talking about how unhappy they are with the impacts of the project on their own departments. Stakeholder A asks I the project is on time, and Stakeholder B replies that the SPI is 1.05. Stakeholder A asks if the project manager for the project knows o Stakeholder B’s concern. Stakeholder B responds that he is not sure. What is the BEST thing for the project manager to do?

  1. Make sure stakeholders see that the project manager overheard. Then ask them to direct any questions to the project manager in writing.
  2. Make a presentation to all the stakeholders regarding the status of the project.
  3. Send both stakeholders a copy of the issue log, and ask for additional comments.
  4. Arrange a meeting with both stakeholders to allow them to voice any concerns they may have.
Correct Answer

Q6. Quality on your project must be as high as possible, yet this type of project is new for your company. Which of the following is the BEST thing to do?

  1. Audit work as it is being completed to look for any needed improvements
  2. Improve your work authorization system
  3. Use cause and effect diagrams when there is a defect
  4. Make sure your staffing management plan is up to date.
Correct Answer

Q7. A project has seven activities: A, B, C, D, E, F, and G. Activities A, B, and D can start anytime. Activity A takes 3 weeks, activity B takes 5 weeks, and Activity D takes 11 weeks. Activities A and B must be completed before Activity C can start. Activity C requires 6 weeks to complete. Activities B, C, and D must be completed before Activity E can start. Activity E requires 2 weeks. Activity F takes 4 weeks and can start as soon as activity C is completed. Activity E must be completed before activity G starts. Activity G requires 3 weeks. Activities F and G must be completed for the project to be completed. Which activities have float available?

  1. Activity A has two weeks float, activity F has one week
  2. Activity F has one week float
  3. There is no float available in the project.
  4. Activity A has eight weeks float
Correct Answer

Q8. The Budget at Completion (BAC) for a project is $50,000. The Actual Costs (AC) to date are $10,000. The Earned Value (EV) is $7,000. At this stage, the project management team did a manual bottom-up summation of costs and forecast an Estimate to Complete (ETC) of $50,000. What is the Estimate at Completion (EAC) for the project?

  1. $57,000
  2. $40,000
  3. $60,000
  4. $53,000
Correct Answer

Q9. You are the project level manager with several project activities underway. In the executing process group, you begin to become concerned about the accuracy of progress reports from the projects. What would BEST support your opinion that there is a problem?

  1. Quality audits
  2. Risk quantification reports
  3. Regression analysis
  4. Monte Carlo analysis
Correct Answer

Q10. All of the following could occur during the Close Process or Phase process EXCEPT:

  1. Creating lessons learned
  2. Formal acceptance
  3. Reducing resource spending
  4. Performing benefit cost analysis
Correct Answer










User Agreement| |Privacy Policy