IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs Personality Tests Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Project Management - Question 1:

Which of the following is not an example of data that may be presented in a performance report?

  1. Earned value
  2. Quality metrics
  3. Schedule variance
  4. Project charter






Project Management- Q2. There is a probability of 0.1 that a given risk will occur in a project. If it occurs, it will result in a loss of US $10,000. The insurance cost for this event is US $700, with a deductible amount of US $250. Should a rational project manager buy this insurance?

  1. Yes, since $1,000 > $950.
  2. Yes, since $1,000 > $700.
  3. No, since the deductible amount changes the expected monetary value of the risk event.
  4. No, since $1,250 > $1,000.
Correct Answer


Project Management- Q3. A cost performance plan contains a description of:

  1. The project costs.
  2. How resources are allocated.
  3. The budgets and how they were calculated.
  4. The WBS level at which earned value will be calculated.
Correct Answer


Project Management- Q4. The work breakdown structure can be BEST thought of as an effective aid for _________ communications.

  1. Team
  2. Project manager
  3. Customer
  4. Stakeholder 13
Correct Answer


Project Management- Q5. The Code of Ethics and Professional Conduct has as its foundation four values identified by practitioners from the global project management community. They are:

  1. Respect, fairness, transparency, and freedom
  2. Responsibility, transparency, fairness, and honesty
  3. Respect, freedom, honesty, and transparency
  4. Responsibility, respect, fairness, and honesty
Correct Answer


Project Management- Q6. Which of the following is a TRUE statement about a risk rating matrix?

  1. It should be changed for every product
  2. It should never be used on a large project
  3. It should be standardized between projects
  4. It should be developed by the project manager.
Correct Answer


Project Management- Q7. Which of the following BEST describes what a project charter may be used for when the work is being completed?

  1. To make sure all the team members are rewarded
  2. To help determine if a scope change should be approved
  3. To assess the effectiveness of the change control system
  4. To make sure that all the documentation on the project is completed
Correct Answer


Project Management- Q8. During a project, a team member tells you that a major risk identified by the team has occurred. However, it is not as serious as previously thought. What is the FIRST thing you should do?

  1. Increase the quality standard
  2. Present this finding to the project team and ask them to verify the team member’s finding
  3. Investigate changing the contingency plan
  4. Notify management
Correct Answer


Project Management- Q9. Which of the following allows a project management team to communicate all approved and rejected changes to the stakeholders consistently?

  1. Configuration management system
  2. Verification management system
  3. Configuration status accounting
  4. Change management board
Correct Answer


Project Management- Q10. Which of the following is a tool or technique of the Manage Stakeholder Engagement process?

  1. Communication technology
  2. Communication models
  3. Communication standard
  4. Communication skills
Correct Answer











User Agreement| |Privacy Policy
© 2026 - Tag&Link – Mostafa Taha Mohamed