Question:

Your project team is having a dispute with a vendor about whether a specific task is within the project’s scope. The scope statement does not provide implementation-level details that could resolve this dispute. There is no WBS, however, because the project sponsor insisted that the project be started right away without pausing to create standard project planning documentation. Who is at fault?
  1. The project manager
  2. The project sponsor
  3. The project stakeholders
  4. The project vendor






Q2. During project executing, a large number of changes are made to the project. The project manager should:

  1. Wait until all changes are known and print out a new schedule
  2. Make sure the project charter is still valid
  3. Change the schedule baseline
  4. Talk to management before any changes are made
Correct Answer

Q3. Adaptive project lifecycles, in comparison with predictive project lifecycles, are developed with the intent of:

  1. Eliminating cost of changes throughout the project’s lifecycle
  2. Providing agility in responding to change
  3. Maximizing cost of changes throughout the project’s lifecycle
  4. Minimizing cost of changes throughout the project’s lifecycle
Correct Answer

Q4. Many organizations consider contract administration to be an administrative function separate from the project organization. Who carries out the function of contract administration in such organizations?

  1. The Project Manager
  2. The Procurement Advisor
  3. The Procurement Administrator
  4. The Contract Advisor
Correct Answer

Q5. You are collecting requirements for your project. For a few requirements you are having difficulty reaching a consensus, so you decide to vote and select the choice which has the largest number of votes. What voting technique is this?

  1. Minority
  2. Unanimity
  3. Majority
  4. Plurality
Correct Answer

Q6. You created the logic diagram for your project based on the chart when all of a sudden the person completing activity C says that you must plan for a lag of two weeks after the completion of the activity before starting the next activity. Which of the following would be the FIRST thing to do?

  1. See if the duration of activity H can be shortened
  2. Nothing because the two weeks could be assigned to activity
  3. Make Start, A, D, G, End the critical path in order to save time
  4. Calculate project float after the insertion of the lag
Correct Answer

Q7. A number of identified risks occurred early in a project. As a result, most of the project objectives ended up in jeopardy. The project manager decided to present a case to management that the project be closed down. This is an example of:

  1. Risk Acceptance
  2. Risk Mitigation
  3. Risk Avoidance
  4. Risk Transfer
Correct Answer

Q8. All requested changes to a contract go through Contract Change Control Systems of both parties. The Contract Change Control system documents all requested changes for future reference. However, requested but unresolved changes might not make it up to either party’s Change Control Systems. If you are contesting a dispute, where can you find a record of such requested changes?

  1. Procurement management plan
  2. Project management plan
  3. Project correspondence
  4. Approved change requests log
Correct Answer

Q9. The halo effect refers to the tendency to:

  1. Promote from within
  2. Hire the best
  3. Move people into project management because they are good in their technical fields
  4. Move people into project management because they have had project management training.
Correct Answer

Q10. While conducting interviews for a project manager position, you notice that your classmate is one of the prospective candidates. What should you do immediately?

  1. Encourage your classmate by offering some tips
  2. Resign from the interview panel
  3. Remove your classmate from the list
  4. Inform the interview panel of the relationship
Correct Answer