IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

For which of the following actions could a project manager incur a fine and be jailed?
  1. Using people from outside the project manager’s country to work on the project
  2. Failing to file the necessary permits in their own country
  3. Paying a bribe to a foreign official
  4. Not using minority workers on the project






Q2. Which of the following is Deming's method for continuous improvement?

  1. Plan-Act-Check-Do
  2. Plan-Do-Check-Act
  3. Check-Plan-Do-Act
  4. Plan-Check-Do-Act
Correct Answer

Q3. You are developing the project management plan. Management asks you to provide them with information on the chances of completing the project under different circumstances. The project is important and so management does not want to delay the schedule. You compile the data and use a tool and tell management that there is a 90% chance you can complete the project within the schedule, however, if you are given three weeks of extra time, the chance of completing project rises to 98%. Which of the following statements is true about the tool you have used to come up with this information?

  1. It is a perform qualitative risk analysis process technique
  2. It is a perform quantitative risk analysis process technique
  3. It is a control quality process technique
  4. It is a technique of the determine budget process
Correct Answer

Q4. In a small office construction project, the following activities are scheduled in sequence. i) Digging and pouring footings: five days. ii) Working on the slab and pouring: three days. iii) Framing the floor: five days. iv) Wall framing: four days. v) Roof framing: six days. vi) Insulation and drywall: seven days. vii) Interior doors and trim: three days. viii) Hardware and fixtures: two days. What is the minimum time to complete the project if all activities are on a critical path except activity viii, and activity iii is delayed by one day?

  1. 32 days
  2. 33 days
  3. 34 days
  4. 35 days
Correct Answer

Q5. The current update to the schedule performance report shows no schedule variance. Based upon this report, you tell the client that the project is on time. However, your team members know that you just missed a major milestone and the project will not meet its startup date. This is an indication of poor:

  1. Communications planning.
  2. Scope planning.
  3. Team trust.
  4. Schedule planning.
Correct Answer

Q6. Who of the following has primary responsibility for establishing design and test specifications?

  1. Senior management
  2. Procurement
  3. Engineering
  4. Quality control
Correct Answer

Q7. A project manager has just been assigned to a project that has been in progress for two months when a team member requests more time on an activity he is working on. The project manager discovers that the only impact to the project will be a delay on a noncritical path activity. The customer has emphasized the importance of completing the project on schedule. What should the project manager do NEXT?

  1. Submit the information to the change control board, determine if this event might impact the team member’s future work, inform the team member of the board’s decision
  2. Ask the team member why they need more time, begin integrated change control, adjust the project schedule as needed
  3. Look for impacts to quality, cut unneeded scope from the project, ask for more resources
  4. See if any stakeholders object to the change, calculate the exact impact on the project, look at removing this resource from the project
Correct Answer

Q8. You have joined a new organization and are assigned a project. This is a new type of project but the organization has completed many similar projects in the past. You decide to review the lessons learned from past projects. You go to the archives and ask for the lessons learned from past projects. Lessons learned is a part of which of the following?

  1. Organizational process assets
  2. Enterprise environment factor
  3. Project management plan
  4. Project archive
Correct Answer

Q9. The stakeholder engagement plan is a subsidiary plan of the project management plan. It includes the strategies required to effectively engage project stakeholders. An ineffective stakeholder engagement strategy can lead to project failure. The stakeholder engagement plan:

  1. Must be formal and highly detailed
  2. Must be formal but broadly framed
  3. Can be formal or informal but must be highly detailed
  4. Can be formal or informal, highly detailed or broadly framed
Correct Answer

Q10. The customer responsible for overseeing your project asks you to provide a written cost estimate that is 30 percent higher than your estimate of the project’s cost. He explains that the budgeting process requires manager to estimate pessimistically to ensure enough money is allocated for projects. What is the BEST way to handle this?

  1. Add the 30 percent as a lump sum contingency fund to handle project risks
  2. Add the 30 percent to your cost estimate by spreading it evenly across all project activities
  3. Create one cost baseline for budget allocation and a second one for the actual project management plan.
  4. Ask for information on risks that would cause your estimate to be low.
Correct Answer










User Agreement| |Privacy Policy