IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

You are in the Validate Scope process of your electronic goods manufacturing project. While reviewing some products, you have noticed that the tolerance for one product is 0.01 percent less than what was listed in the requirements documentation. This deviation may not be a problem for the customers, and it may not impair the product’s operation. What is your best immediate action in such a situation?
  1. Notify the stakeholders about the deviation
  2. Change the project management plan to allow for small deviation
  3. Reject all products and restart the project
  4. Discuss with your team about the quality testing






Q2. Management wants to be sure that the project is following defined quality standards. Which of the following should they look at?

  1. Risk management plan
  2. WBS
  3. Statement of work
  4. Quality audit
Correct Answer

Q3. During the implementation of a contingency plan, a team member notices that the plan worked only marginally. There were three similar contingency plans developed for other risks that have not yet happened. He should recommend which of the following?

  1. A workaround
  2. A project change request
  3. A new risk rating matrix
  4. A risk responsibility chart review
Correct Answer

Q4. What do the buyer and seller have in common with regard to Control Procurements?

  1. Both parties ensure that they meet their contractual obligations and that their own legal rights are protected.
  2. Both parties have specific resources that can be idle.
  3. Both parties have a contract change management plan.
  4. Each party has its own project plan and legal team.
Correct Answer

Q5. A project uses rounding of activity cost estimates data to the nearest $100, uses staff hours as the unit of measure for resources, and has a variance threshold of 10 percent deviation from the baseline plan. These approaches are typically documented in the:

  1. Cost management plan
  2. Scope Statement
  3. WBS
  4. Project charter
Correct Answer

Q6. A business is considering more than a dozen infrastructure upgrade projects. These projects, once delivered, will add to the organization’s overall performance but will not contribute to any of the revenue streams. Prior to initiating any such project, the value of the project to the organization must be determined. Which of the following is the most important factor to consider in such a scenario?

  1. Net Present Value (NPV) of the projects
  2. Internal Rate of Return (IRR) of the projects
  3. Alignment with the strategic goals
  4. Investment requirement
Correct Answer

Q7. Three years back, your organization awarded a fixed price contract to a reputable local contractor to construct a new airport terminal in the city. A few days back, you received a change request from the contractor requesting to adjust the contract’s price. The contractor is claiming that as a result of the recent national recession, the prices of raw materials have gone up and he cannot complete the rest of the project at the contract price. Is the contactor’s request legitimate?

  1. Yes, you cannot penalize the contactor for price escalations due to force majeure.
  2. Yes, unless there is no Economic Price Adjustment provision in the contract.
  3. No, the price of the contract is fixed and cannot be changed.
  4. No, the price hike due to recession must be adjusted against the contractor’s profit.
Correct Answer

Q8. What is the duration of the near-critical path based on the chart?

  1. 33
  2. 44
  3. 31
  4. 43
Correct Answer

Q9. During the development of the project stakeholder engagement plan, the project manager is usually dependent on the expert judgment of senior stakeholders to identify and plan effective stakeholder management strategies. Which of the following stakeholders cannot guide the project manager in developing effective strategies for internal stakeholders?

  1. Sponsor
  2. Identified key stakeholders
  3. Customers
  4. Project team members
Correct Answer

Q10. After a great deal of effort, the project team has finally determined the specifications for a major scope change to the project. In light of this, what should the project manager do FIRST?

  1. Look for other changes
  2. Notify the stakeholders about the new scope
  3. Gain sign-off on this change
  4. Calculate the risks associated with this change
Correct Answer










User Agreement| |Privacy Policy