IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Project Management Question Bank
for Exam preparation

Select Knowledge area

Question:

An activity needs more time because an identified risk has occurred. The project manager determines that there is enough reserve to accommodate the change. Who needs to approve the change?
  1. Management
  2. Project manager
  3. Team member
  4. Functional manager






Q2. While analyzing a project, the project manager calculated the ratio of the Earned Value (EV) to the Actual Costs (AC) and obtained a value of 1.2. The project manager decided this was an unfavorable condition for the project and decided to take corrective action. What is your view?

  1. The project manager is correct. The ratio of EV to AC is the Cost Performance Index and a ratio greater than 1 is unfavorable to the project
  2. The project manager is not correct. The ratio of EV to AC is the Cost Variance and a ratio greater than 1 is favorable to the project.
  3. The project manager is not correct. The ratio of EV to AC is the Cost Performance Index and a ratio greater than 1 is favorable to the project
  4. The project manager is correct. The ratio of EV to AC is the Cost Variance and a ratio greater than 1 is unfavorable to the project.
Correct Answer

Q3. Which list includes a process where recommended corrective action is NOT an output?

  1. Control Quality, Control Costs, Report Performance
  2. Control Costs, Manage Quality, Direct and Manage Project Work
  3. Control Scope, Distribute Information, Control Risks
  4. Monitor and Control Project Work, Manage Stakeholder Expectations, Manage Quality.
Correct Answer

Q4. Which of the following is a common problem in the Close Project or Phase process?

  1. Retaining resources to complete the project
  2. Completing the quality assurance plan
  3. Obtaining scope verification
  4. Completing a project charter
Correct Answer

Q5. You are working as the project manager on a mega-construction project. You need to prepare a quarterly report for the project investors. You need to collect work performance data and convert that into work performance information. Which of the following processes produces work performance data?

  1. Direct and Manage Project Work
  2. Control Schedule
  3. Control Costs
  4. Manage Communications
Correct Answer

Q6. All of the following statements concerning procurement documents are incorrect EXCEPT:

  1. Well-designed procurement documents can simplify comparison of responses.
  2. Procurement documents must be rigorous with no flexibility to allow consideration of seller suggestions.
  3. In general, procurement documents should not include selection criteria.
  4. Well-designed procurement documents do not include a procurement statement of work.
Correct Answer

Q7. There have been numerous changes on your project. All approved changes are BEST reflected in the:

  1. Performance measurement variance
  2. Validate Scope process
  3. Change control procedures
  4. Project management plan
Correct Answer

Q8. Which of the following estimating techniques will cost less but is also typically less accurate?

  1. Parametric Estimating
  2. Analogous Estimating
  3. Resource Cost-based Estimating
  4. Bottom-up Estimating
Correct Answer

Q9. Which type of cost is team training?

  1. Direct
  2. NPV
  3. Indirect
  4. Fixed
Correct Answer

Q10. Your project calls for communication with an extremely large audience. What communication method would be appropriate under such circumstances?

  1. Pull communication
  2. Interactive communication
  3. Two-way communication
  4. Verbal communication
Correct Answer










User Agreement| |Privacy Policy