Question:

In the create WBS process, you sub-divide project deliverables and project work into smaller and more manageable components. The output of this process is the scope baseline and project document update. Which of the following truly represents the scope baseline?
  • Scope statement, scope management plan, schedule baseline
  • Scope statement, WBS, WBS dictionary
  • WBS, WBS dictionary
  • Scope statement, WBS, schedule baseline