Question:

You are a risk manager of a project and the project manager has given you the responsibility of developing the risk management plan. So, you start collecting the risks and then you categorize them based on their impact on the project objectives. Afterward, you analyze them and develop the risk response plan for positive risks and negative risks. After developing these response plans, what will your next step be?
  • Develop the risk response plan for neutral risks
  • Update the project management plan
  • Assign the risk action owner to each risk
  • Change the critical path to reflect the risk impact