You gave the responsibility of collecting requirements from project stakeholders to four of your team members. After starting the requirements collection process one of your team members left the job and the requirements could not be compiled properly. Initially, you did not notice this, however, during a product review, a few stakeholders told you that some of the features in the products were not requested by them. Therefore, to verify their comments you review the product requirements and identify the issue. This is an example of:
  • Scope creep
  • Scope slippage
  • Gold plating
  • Opportunity