Your project is ahead of schedule but over budget. Therefore, you ask your team member to collect data and compare it with the cost baseline. Which of the following is not included in the cost baseline?
  • Contingency reserve
  • Activity cost estimation
  • Management reserve
  • Activity contingency reserve