Quality - Question 1:

The standard normal distribution has mean= ______________ and standard deviation= ______________.

  1. 1,0
  2. 0,1
  3. 0,0
  4. 1,1






Quality- Q2. According to Deming most of the problems are related to systems and it is the responsibility of the management to improve the systems

  1. correct
  2. correct to some extent
  3. correct to great extent
  4. Taguchi
Correct Answer


Quality- Q3. Quality Circles members are ______________

  1. Paid according to their contribution to quality
  2. External consultants designed to provide training in the use of Quality tools
  3. Always machine operators
  4. None of the three.
Correct Answer


Quality- Q4. The primary components of quality management are quality ______________.

  1. insurance, assurance, and warranty
  2. inspections, certifications, and validations
  3. philosophy, assurance, and control
  4. form, fit, and function
  5. reliability, maintainability, and availability
Correct Answer


Quality- Q5. A fan blade is specified by length and thickness. While sampling, it was found that for one particular blade, the length was non-conforming while the thickness was as per specifications. Should the blade be considered non-conforming for construction of a p chart?

  1. Yes
  2. No
Correct Answer


Quality- Q6. A histogram ordered by frequency of occurrence that shows how many results were generated by each identified cause is:

  1. Pareto Diagram
  2. Statistical Histogram
  3. Juran Histogram
  4. Fishbone Diagram
Correct Answer


Quality- Q7. R charts are used for controlling ______________ of a process.

  1. Central Tendency
  2. Dispersion
  3. None of the above
  4. Both a and b
Correct Answer


Quality- Q8. Which of the following statements is NOT true about charting variation?

  1. A mean and standard deviation will completely define a normal curve
  2. A histogram helps understand process performance
  3. A histogram is sufficient to chart variation
  4. Run charts display process performance over time
Correct Answer


Quality- Q9. Consider that for a particular process, the p has shifted to .4 and the process has gone out of control. The corresponding value of beta is found to be .3356. The value of Average Run Length is:

  1. 2.5
  2. 1.5 ((1/1-beta) provides us with average run length)
  3. 1.0
  4. 2.7
Correct Answer


Quality- Q10. The focal point of all quality control should be:

  1. Price focus
  2. Cost Focus
  3. Customer Focus
  4. Manufacturing Focus
Correct Answer