Question:

Which of the below is not one of the seven quality management principles?
  1. Customer focus
  2. Leadership
  3. Planning
  4. Improvement






Q2. Deming's 4 step cycle for improvement is______________

  1. plan, do, check, act
  2. schedule, do, act, check
  3. do, act, check, monitor
  4. plan, control, act, sustain
Correct Answer

Q3. Quality applies to which aspect(s) of the organization?

  1. Products only
  2. Products and services
  3. People and product
  4. Products, services, and people
Correct Answer

Q4. What is the purpose of a simple linear regression?

  1. To predict scores on a dependent variable from scores on a single independent variable
  2. To predict scores on an independent variable from scores on a single dependent variable
  3. To predict scores on an independent variable from scores on multiple dependent variables
  4. To predict scores on a dependent variable from scores on multiple independent variables
Correct Answer

Q5. The pillars of quality is (are)

  1. B and C
  2. Quality is free
  3. Doing it right the first time
  4. Zero defects
  5. Process improvement
Correct Answer

Q6. DMAIC is ______________

  1. develop, multiply, analyze, improve, check
  2. define, muliply, analyze, improve, control
  3. define, measure, analyze, improve, control
  4. define, manufacture, analyze, improve, control
Correct Answer

Q7. 80% of the problems are found in 20% of the work is a concept of:

  1. Edward Deming
  2. Philip Crosby
  3. Juran
  4. Pareto
Correct Answer

Q8. For new product development, the chosen methodology should be

  1. DMADV
  2. DMAIC
  3. Structured Design Methodology
  4. DMIE
Correct Answer

Q9. In accordance with ISO 9001:2015, which of the following requires documented information to be retained by the organization?

  1. Evidence of competence
  2. Internal audit results
  3. Management review results
  4. All of the above
  5. None of the above
Correct Answer

Q10. The chart used for tracking number non-conforming is:

  1. P
  2. Np
  3. X bar
  4. None of the above
Correct Answer