IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Quality Question Bank
for Exam preparation

Select Knowledge area

Question:

SIPOC
  1. Suppliers, Inputs, Procedure, Outputs, Customers
  2. Simple, Inputs, Process, Outputs, Complex
  3. Simple, Inputs, Procedure, Outputs, Complex
  4. Suppliers, Inputs, Process, Outputs, Customers






Q2. Quality control is the technical processes that ______________ the project's progress against the performance standards.

  1. examine, analyze, and report
  2. inspect, certify, and verify
  3. inspect, examine, and determine
  4. identify, measure, and report
  5. reveal, establish, and record
Correct Answer

Q3. An unbiased dice is rolled once. The probability of getting a number greater than 4 is:

  1. ¼
  2. 1/6
  3. ½
  4. 1/3
Correct Answer

Q4. Quality planning is:

  1. evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards
  2. taking action to increase the effectiveness and efficiency of the project so as to provide added benefits to both the performing organization and the project customer
  3. assuring the production of goods that meet the highest standards of luxury
  4. identifying which quality standards are relevant to the project and determining how to satisfy them
  5. monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance
Correct Answer

Q5. Best price or zero cost is

  1. do not reach the customers
  2. Cost leadership
  3. To keep defective products aside, ensuring they
  4. Prerogative cost
  5. To count, grade, and rework
Correct Answer

Q6. Quality management deals with all of the following topics except:

  1. Conformance to requirements / specifications
  2. Satisfying the needs of the customer
  3. Making products more desirable and luxurious
  4. A and C
  5. B and C
Correct Answer

Q7. Which are the best two charts to show trends in a process?

  1. Gantt and CPM
  2. Pareto and Control
  3. Control and Run
  4. Histogram and Run
  5. Gantt and Pert
Correct Answer

Q8. Let p0 be the incoming fraction defective and p1 be the outgoing fraction defective (Assume both p1 and p0 is greater than 0). If rectifying inspection is performed then:

  1. P0
  2. P1
  3. None of the above
  4. Cannot be determined
Correct Answer

Q9. The focal point of all quality control should be:

  1. Price focus
  2. Cost Focus
  3. Customer Focus
  4. Manufacturing Focus
Correct Answer

Q10. Measurement accuracy is attained when...

  1. Different people get the same result when measuring the same item or characteristic.
  2. The same person taking multiple measurements on the same item or characteristic gets the same results every time.
  3. The measured value has little deviation from the actual value.
  4. When the resolution of the measurement instrument can give at least 5 distinct values in the range being measured.
Correct Answer










User Agreement| |Privacy Policy