Question:

Quality planning is:
  1. evaluating overall project performance on a regular basis to provide confidence that the project will satisfy the relevant quality standards
  2. taking action to increase the effectiveness and efficiency of the project so as to provide added benefits to both the performing organization and the project customer
  3. assuring the production of goods that meet the highest standards of luxury
  4. identifying which quality standards are relevant to the project and determining how to satisfy them
  5. monitoring specific project results to determine if they comply with relevant quality standards and identifying ways to eliminate causes of unsatisfactory performance






Q2. The main purpose of a stratification plan is:

  1. To prove statistical validity
  2. Define categories to slice and dice the data
  3. Determine which statistical tool to use
  4. To identify solutions
Correct Answer

Q3. The main purpose of the Define Phase is to:

  1. Select a project
  2. Get agreement on the project’s purpose, goals and opportunity
  3. Select a team
  4. Decide on which data to collect
Correct Answer

Q4. The probability of getting a multiple of 2 on throwing a dice once is:

  1. 1/6
  2. ¼
  3. ½
  4. 1/3
Correct Answer

Q5. What is the benefit of an organisation adopting a quality management system?

  1. Facilities opportunities to enhance customer satisfaction
  2. All of the above
  3. Addresses risks and opportunities to enhance customer satisfaction
  4. Improves the organisations overall performance and provides a sound basis for sustainable development initiatives
Correct Answer

Q6. The major purpose of the Control Phase in DMAIC is to:

  1. Identify root causes
  2. Determine long term solutions
  3. Maintain the gains made with implemented solutions
  4. Calculate Cp and Cpk
Correct Answer

Q7. In a double sampling plan, let d1 be the number of defects in the first sample and d2 be the number of defects in the second sample. Let c2 be the acceptance number for both samples. The condition for rejection is:

  1. D1+d2
  2. D1+d2>c2
  3. D1*d2>c2
  4. D1*d2
Correct Answer

Q8. A control limit

  1. Indicates the boundary of the bell curve in a normal distribution
  2. Indicates that a process event or measurement is likely to fall within that limit
  3. Indicates that a process event or measurement is likely to fall outside that limit
  4. Indicates the customer's desired upper or lower performance limits
Correct Answer

Q9. In a normal distribution 68% of the data will occur within...

  1. +/- 2 standard deviations
  2. +/- 1 standard deviation
  3. +/- 3 standard deviations
  4. Outside the bell-shaped curve
Correct Answer

Q10. The main purpose of the Measure Phase of DMAIC is to:

  1. Determine the customer requirements
  2. Find root causes