Quality - Question 1:

Which ISO standard provides guidelines for codes of conduct for organisations, including guidance to an organisation in determining that its customer satisfaction provisions meet customer needs and expectations?

  1. ISO 10007 Quality management systems
  2. ISO 10012 Measurement management systems
  3. ISO 10001 Quality management
  4. ISO 10005 Quality management systems






Quality- Q2. Effective quality control results in:

  1. Increase in customer satisfaction
  2. Lower cost
  3. None of the above
  4. Both a and b
Correct Answer


Quality- Q3. The key process input variables (KPIV) and key process output variables are developed during the ______________ phase.

  1. Define
  2. Analyze
  3. Measure
  4. Improve
Correct Answer


Quality- Q4. The 'Father' of statistical quality control is:

  1. Joseph M. Juran
  2. Philip Crosby
  3. Walter Shewhart
  4. F. W. Taylor
Correct Answer


Quality- Q5. The Operating characteristic curve shows the relationship between the probability of acceptance (on y axis) and ______________ (on x axis).

  1. Proportion defective
  2. Proportion acceptable
  3. Number of lots
  4. Size of lot
Correct Answer


Quality- Q6. For a set of data, the average squared deviation from the mean, with a denominator of n-1

  1. Sample Variance
  2. Normal Distribution
  3. Sample
  4. Population
Correct Answer


Quality- Q7. The value of Var(3 - 4X) is:

  1. 5120 / 9
  2. 1280 / 81
  3. 5120 / 81
  4. 1280 / 9
Correct Answer


Quality- Q8. Which is not a commonly used quality management tool?

  1. Fishbone diagram
  2. CSSR report
  3. Pareto chart
  4. Control chart
  5. None of the above (all are commonly used)
Correct Answer


Quality- Q9. Within ISO 9001:2015, what does “shall” indicate?

  1. a recommendation
  2. a permission
  3. a capability
  4. a requirement
Correct Answer


Quality- Q10. Given L=3 and p=.03, estimate the sample size that can be used for construction of a p chart.

  1. 534
  2. 321
  3. 123
  4. 291 ((1-p)*L2/p gives us an estimate of sample size)
Correct Answer