IRGST

Home Question Bank Online Exams Job Interview Q&A Job Description How To Quotes and Sayings Articles Jobs In Mirrors Personality Types About Contact Us Sign in/up

Quality Question Bank
for Exam preparation

Select Knowledge area

Question:

The Japanese Quality Control (QC) Circle movement motivated its participants in many ways. Which of the following represents the most important motivation for the QC circle participant:
  1. Improving the performance of the company
  2. Self-Improvement
  3. Financial Incentives
  4. Recognition among co-workers
  5. Strengthening of relationships between co-workers






Q2. For a c chart, the OC curve plots the ______________ against ______________.

  1. Probability of Type 2 error, true mean number of defects
  2. Probability of Type 1 error, true mean number of defects
  3. Probability of Type 1 error, true total number of defects
  4. Probability of Type 2 error, true total number of defects
Correct Answer

Q3. If only ______________ causes of variation are present, the output of a process forms a distribution that is table over time and is predictable.

  1. Assignable
  2. Non-Random
  3. Natural
  4. Cannot be said
Correct Answer

Q4. Total quality costs include:

  1. Prevention costs
  2. Appraisal costs
  3. Failure costs
  4. All of the given options
Correct Answer

Q5. The taste of the burger can be categorized as good or bad This is an example of which type of data:

  1. Variable
  2. Attribute
  3. Cannot be determined
  4. None of the above
Correct Answer

Q6. What does the lean manufacturing aims to?

  1. Outsource much of our manufacturing in order to focus on final assembly
  2. Produce goods using less resources compared to mass production techniques
  3. Produce products with fewer options to simplify consumer choices
  4. Keep labor costs as low as possible by using more of other resources
Correct Answer

Q7. ______________ is not a process tools for TQM systems

  1. process flow analysis
  2. histograms
  3. plier
  4. control charts
Correct Answer

Q8. How does ISO 9000:2015 define a process?

  1. Set of interrelated or interacting activities which uses inputs to deliver a result that meets or exceeds the ISO 9001 standards of quality
  2. A full lifecycle of events which includes inputs such as materials and information, management, resources and outputs
  3. A cycle which includes inputs, actions and outputs to ensure quality is met
  4. Set of interrelated or interacting activities that uses inputs to deliver an intended result
Correct Answer

Q9. How many dependent variables does a two-way ANOVA have?

  1. One
  2. Two
  3. Three
  4. Four
Correct Answer

Q10. For a Poisson distribution:

  1. The mean is greater than the variance
  2. The mean is less than variance
  3. The mean is equal to the variance
  4. Cannot be determined
Correct Answer










User Agreement| |Privacy Policy